Key highlights
✓ Stage two avionics trays, harnessing, valves, and raceways installed as integration advances
✓ Software run-for-record testing began following completion of the stage two HITL build
✓ All first stage Aeon R flight one engines have been manufactured, assembled, and shipped
✓ Aeon V completed full-duration mission duty cycles and achieved key service life milestones
✓ LC-16 water tower completed its fourth lift, reaching 275 feet tall
Chapters
0:00 – 0:13 Introduction
0:14 – 0:25 Design Overview
0:26 – 1:36 Build Overview
1:37 – 2:38 Test Overview
2:39 – 3:06 Launch Overview
3:07 – 3:19 Closing Recap
Stay Connected
🚀Terran R
🚀Careers
✓ Stage two avionics trays, harnessing, valves, and raceways installed as integration advances
✓ Software run-for-record testing began following completion of the stage two HITL build
✓ All first stage Aeon R flight one engines have been manufactured, assembled, and shipped
✓ Aeon V completed full-duration mission duty cycles and achieved key service life milestones
✓ LC-16 water tower completed its fourth lift, reaching 275 feet tall
Chapters
0:00 – 0:13 Introduction
0:14 – 0:25 Design Overview
0:26 – 1:36 Build Overview
1:37 – 2:38 Test Overview
2:39 – 3:06 Launch Overview
3:07 – 3:19 Closing Recap
Stay Connected
🚀Terran R
🚀Careers
Comments 0
Be the first to comment!